Installation Process FAVEMANC Ventilated Façade Systems :
 

  • On-site laying plan for framing parts placement
  • Fixing of supporting brackets on each slabs and fixing of retaining bracket about each meter
  • T profile placement
  • Joint profiles.
  • Laying of insulation coat leaving at least a 3 cm ventilated chamber
  • Fixing ceramic plate using a fastener clip screwed to profile
  • Placement order of the ceramic plates
  • Resin bed on profile,  only at one of the ends of the ceramic plate
  • Finish façade